Laying of 10” Gas Pipeline

Laying of 10” Gas Pipeline

ClientSyrian Company for Oil Transport (SCOT/Banias)
LocationBanias
Date2010

Project Information

Construction of a 60 km, 10-inch gas pipeline linking Pumping Station T2 to the Syrian–Iraqi border.

Scop of Work

60 km gas pipeline - Onshore construction - Mechanical and civil works

Construction Planning

R&T constructed a 60 km, 10-inch gas pipeline linking Pumping Station T2 to the Syrian–Iraqi border. The project included full onshore pipeline construction, mechanical installation, and civil works. The new line expanded regional gas transport capacity and strengthened cross-border energy infrastructure.