Ultrasonic Inspection of Offshore Loading Pipelines – Banias Terminal

/
In 2004, R&T performed an internal ultrasonic inspection of the offshore loading pipelines. The project required specialized inspection techniques both onshore and offshore to assess the condition of the pipelines. Delivered as a turn-key operation, the work provided SCOT with critical diagnostic data on pipeline integrity, enabling informed maintenance decisions and ensuring the safe continuity […]

Construction of 26” Launcher & Receiver Stations with Inline Inspection

/
In 2009, R&T delivered a major upgrade to Syria’s pipeline inspection infrastructure by constructing skid-mounted launcher and receiver stations for 26-inch pipelines at two strategic locations: Banias and Al-Loweibde (Homs). The stations were engineered to support multiple inline inspection types (cleaning, geometric, and intelligent pigs), enabling comprehensive inline inspection and long-term integrity management.

EPC – Alhosain Gas Project Station

/
R&T undertook the EPC contract for the Alhosain Gas Project Station. The project encompassed the engineering, procurement, and construction of critical gas infrastructure, integrating mechanical, electrical, and civil systems.

Maintenance Service Contract – Al-Furat Petroleum

/
R&T participated in the execution of a major maintenance service contract for Al-Furat Petroleum Company. The assignment included comprehensive operational support services, equipment servicing, and field maintenance activities. The project strengthened asset reliability across key petroleum fields and reinforced R&T’s long-standing reputation in Syria’s upstream operations.

Intelligent Inline Inspection– 26” Pipeline

/
R&T conducted an inline intelligent inline inspection for the 26-inch pipeline. Using advanced tools to detect corrosion, dents, laminations, and anomalies, the project provided a complete pipeline integrity assessment. A detailed evaluation report and repair recommendations were delivered, enabling SCOT to plan and prioritize maintenance activities based on accurate, high-resolution data.

Intelligent Inline Inspection– 22” Pipeline

/
Executed in parallel with the 26-inch line, R&T completed an intelligent inline inspection assessment on the 22-inch pipeline. The inspection covered full anomaly detection and produced a complete structural and operational technical evaluation. The project improved safety, ensured compliance, and supported the long-term health of the national pipeline network.

24” Pipeline Construction

/
R&T, working jointly, constructed a 24-inch gas pipeline. The project included field construction, pipeline installation, mechanical works, and safety integration. This assignment contributed to expanding the national gas transmission grid.

Replacing 10” Corroded River Crossing Line with New 6” Pipeline

/
R&T replaced a corroded 10-inch river crossing pipeline segment with a new 6-inch line, addressing critical safety and operational issues. The work involved supplying specialized equipment, ensuring safe installation, and delivering a fully rehabilitated pipeline section designed for long-term reliability.

Ethanol & Methanol Production Plant – Green Field

/
In 2024, R&T completed a full EPC-style project for the construction, supply, and installation of an ethanol and methanol production plant. This project represents a modern industrial development in Syria, integrating mechanical systems, process equipment, and production lines. Delivered as a complete greenfield facility, it expanded local industrial capacity and introduced new production capabilities to […]